2021 Project Update #6
(All work is performed emergency, manpower, and progress permitting; equipment used for construction may be disruptive)
* Begin parapet construction on bridge S-1 over MD 210 SB
* Continue to pour sidewalk at the new Kerby Hill Rd. alignment
* Continue with barrier wall construction at MD 210 median Looking ahead to next week:
• Continue with signal/electrical work at Murray Hill & Livingston.
For more information about this project, please contact Mr. David Jackson, SHA Project Engineer at djackson2@mdot.maryland.gov or Ms. Amy Andrews, SHA District 3 Area Engineer at aandrews@mdot.maryland.gov.